Trench and excavation calculator
Enter the trench length, top width, bottom width and depth to calculate excavation in cubic yards. Trench cubic yards = length × (top width + bottom width) ÷ 2 × depth ÷ 27, which covers both straight-sided and trapezoid trenches.
How trench and excavation calculator works?
The trench and excavation calculator works in 3 steps: it averages the top and bottom widths, multiplies by depth and length for bank cubic feet, divides by 27, and adds swell for the loose volume to haul.
- Enter the trench length.
- Enter the top and bottom widths (equal for straight sides).
- Enter the depth.
- Set the swell and read the volume to haul.
Trench and excavation formula
The trench formula is cubic yards = (top width + bottom width) ÷ 2 × depth × length ÷ 27.
Cross-sectionA = (top + bottom) ÷ 2 × depthBank cubic yardsyd³ = A × length ÷ 27Looseyd³ = bank × (1 + swell)- bank = volume in the ground before digging
- swell = growth in volume after digging, about 25% for common earth
Trench and excavation conversion chart
The trench and excavation conversion chart lists bank cubic yards per 100 ft (30.5 m) of straight-sided trench.
| Width | 2 ft deep | 3 ft deep | 4 ft deep | 5 ft deep |
|---|---|---|---|---|
| 1 ft (0.30 m) | 7.4 | 11.1 | 14.8 | 18.5 |
| 1.5 ft (0.46 m) | 11.1 | 16.7 | 22.2 | 27.8 |
| 2 ft (0.61 m) | 14.8 | 22.2 | 29.6 | 37.0 |
| 3 ft (0.91 m) | 22.2 | 33.3 | 44.4 | 55.6 |
| 4 ft (1.22 m) | 29.6 | 44.4 | 59.3 | 74.1 |
How to Calculate Trench Excavation
To calculate trench excavation, find the cross-section area and multiply by the trench length. There are 3 steps:
- Average the top and bottom widths: (top + bottom) ÷ 2.
- Multiply by the depth for the cross-section in square feet, then by the length for cubic feet.
- Divide by 27 for bank cubic yards, and add 20–30% swell for the loose volume to haul.
A 40 ft trench 3 ft wide at the top, 2 ft at the bottom and 3 ft deep is 11.1 cubic yards (8.5 m³) in place, and about 13.9 cubic yards loose at 25% swell.
Trench Volume per 100 Feet
| Trench (width × depth) | yd³ per 100 ft | m³ per 30 m |
|---|---|---|
| 1 × 2 ft (0.3 × 0.6 m) | 7.4 | 5.6 |
| 1.5 × 3 ft (0.46 × 0.9 m) | 16.7 | 12.5 |
| 2 × 4 ft (0.6 × 1.2 m) | 29.6 | 22.3 |
| 3 × 5 ft (0.9 × 1.5 m) | 55.6 | 41.8 |
Trenches deeper than 5 ft (1.5 m) need shoring or sloped sides under OSHA rules in the US. Check local regulations.
Frequently Asked Questions
How do I calculate excavation in cubic yards?
Multiply length × width × depth in feet and divide by 27. For sloped sides, use the average of the top and bottom widths.
What is the difference between bank and loose cubic yards?
Bank cubic yards measure soil in the ground, and loose cubic yards measure it after digging. Loose soil takes up 20–30% more space.
How do I calculate a trapezoid trench?
Multiply (top width + bottom width) ÷ 2 × depth × length, then divide by 27.
How many cubic yards in a 100 ft trench?
A 100 ft trench 2 ft wide and 3 ft deep holds 22.2 cubic yards (17 m³) in place, and about 27.8 yards loose.
How wide is a trench for a footing?
A footing trench is usually 16–24 inches (41–61 cm) wide for houses, set by the footing design.
Do I subtract the pipe from trench backfill?
Yes, subtract the pipe and bedding volume from the trench volume to find the backfill needed.