cubic yard calculator

Pool and pond excavation calculator

Enter the pool or pond size and the shallow and deep depths to calculate the excavation in cubic yards. Excavation (yd³) = area × (shallow depth + deep depth) ÷ 2 ÷ 27, plus swell for the loose soil to haul away.

Pool or pond excavation with sloped floor
Live preview
Excavation
0

How pool and pond excavation calculator works?

The pool and pond excavation calculator works in 3 steps: it adds the over-dig around the edge, multiplies the dig area by the average of the shallow and deep depths ÷ 27 for bank cubic yards, and adds swell for loose yards and truckloads.

YOU ENTERCALCULATOR DOESYOU GETShapeLengthWidthShallow end depthDeep end depthOver-dig around the edge(L + 2 over) × (W + 2 over)× (d1 + d2) ÷ 2 ÷ 27Bank yd³Loose yd³ to haulTruckloadsDig area
  1. Pick rectangle (pool) or round (pond).
  2. Enter the size and the shallow and deep depths.
  3. Enter the over-dig around the edge.
  4. Set swell and read the loads.

Pool and pond excavation formula

The pool excavation formula is cubic yards = dig area × (shallow depth + deep depth) ÷ 2 ÷ 27.

Dig areaA = (L + 2 × over) × (W + 2 × over), or π ÷ 4 × (D + 2 × over)²Bankyd³ = A × (d1 + d2) ÷ 2 ÷ 27Looseyd³ = bank × (1 + swell)
With your numbers
—

Pool and pond excavation conversion chart

The pool and pond excavation conversion chart lists dig volume for rectangular pools 3.5–6 ft deep with 2 ft over-dig and 25% swell.

PoolBank yd³Loose yd³10 yd³ loads
12 × 24 ft78.898.510
14 × 28 ft101.3126.713
16 × 32 ft126.7158.316
18 × 36 ft154.8193.520
20 × 40 ft185.8232.224
Bank cubic yards by pool size12 × 24 ft79 yd³14 × 28 ft101 yd³16 × 32 ft127 yd³18 × 36 ft155 yd³20 × 40 ft186 yd³
Next step

Count the scoops with the loader bucket calculator. Above-ground pools need a sand pad: see the pool sand calculator.

How to Calculate Pool Excavation

To calculate pool excavation, add the over-dig to each side, multiply length × width × average depth, and divide by 27. A 16 × 32 ft pool with 2 ft over-dig, 3.5 ft shallow end and 6 ft deep end needs 126.7 cubic yards (96.8 m³) of excavation, or 158.3 cubic yards loose at 25% swell: about 16 dump truck loads.

  1. Add the over-dig to every side for wall forms and backfill.
  2. Average the shallow and deep depths.
  3. Multiply length × width × average depth and divide by 27 for bank cubic yards.
  4. Multiply by 1 + swell for the loose volume to haul.

Pond Excavation

A round pond 20 ft across that slopes from 2 ft deep on one side to 5 ft on the other averages 3.5 ft and needs 40.7 cubic yards (31.1 m³) of excavation with no over-dig. A bowl-shaped pond with sloped sides holds less than a straight-sided hole of the same size.

Frequently Asked Questions

How many yards of dirt come out of a pool?

A 16 × 32 ft pool with a 3.5–6 ft depth produces about 127 bank cubic yards with 2 ft over-dig, or 158 loose cubic yards to haul.

How many dump truck loads for a pool dig?

A typical 16 × 32 ft pool dig takes about 16 loads in 10 yard dump trucks after swell.

Why add over-dig to a pool excavation?

Over-dig gives room for wall forms, plumbing and backfill around the pool shell, usually 1–3 ft (0.3–0.9 m) on each side.

How much dirt comes out of a 12x24 pool?

A 12 × 24 ft pool 3.5–6 ft deep with 2 ft over-dig produces about 79 bank cubic yards, or 99 loose yards at 25% swell.

How long does a pool dig take?

A residential pool dig takes 1–3 days with an excavator, depending on soil, access and truck count.

Can I keep pool dirt on site?

Yes, keep some pool dirt for backfill and grading and haul the rest; fill around the pool is usually 10–20% of the dig.