cubic yard calculator

Loader bucket calculator

Enter the bucket size, fill factor and job size to calculate how many loader bucket scoops you need. Scoops = cubic yards to move ÷ (bucket capacity × fill factor), rounded up.

Bucket scoops grouped by truckload
Live preview
Bucket scoops
0

How loader bucket calculator works?

The loader bucket calculator works in 3 steps: it multiplies the heaped bucket capacity by the fill factor for yards per scoop, divides the job by that for scoops, and divides the truck capacity for scoops per truck.

YOU ENTERCALCULATOR DOESYOU GETBucketBucket capacity (heaped)Fill factorMaterial to moveTruck or trailer capacityper scoop = bucket × fill %scoops = job ÷ per scoopBucket scoopsScoops per truckTruckloadsLast scoop size
  1. Pick a bucket size or enter a custom capacity.
  2. Set the fill factor.
  3. Enter the yards to move and the truck capacity.
  4. Read the scoops and loads.

Loader bucket formula

The loader bucket formula is scoops = cubic yards to move ÷ (bucket capacity × fill factor).

Per scoopyd³ = bucket × fill factorScoopsscoops = ⌈job ÷ per scoop⌉Per truck⌈truck ÷ per scoop⌉
With your numbers
—

Loader bucket conversion chart

The loader bucket conversion chart lists scoops to fill a 10 yd³ (7.6 m³) truck by bucket size and fill factor.

Bucket75% fill90% fill100% fill
0.33 yd³ (0.25 m³)413431
0.5 yd³ (0.38 m³)272320
0.75 yd³ (0.57 m³)181514
1 yd³ (0.76 m³)141210
2 yd³ (1.53 m³)765
3.5 yd³ (2.68 m³)443
Scoops per 10 yd³ truck at 90% fill0.33 yd³34 scoops0.5 yd³23 scoops0.75 yd³15 scoops1 yd³12 scoops2 yd³6 scoops3.5 yd³4 scoops
Next step

Size the dig with the trench and excavation calculator, and add swell with the bank, loose and compacted calculator.

How to Calculate Loader Bucket Scoops

To calculate loader bucket scoops, multiply the bucket's heaped capacity by the fill factor, then divide the job's cubic yards by that number and round up. Moving 12 cubic yards with a 1 yard bucket at 90% fill takes 14 scoops, and a 10 yard truck takes 12 scoops.

MachineTypical bucketScoops per 10 yd³ (90% fill)
Compact tractor⅓ yd³ (0.25 m³)34
Small skid steer½ yd³ (0.38 m³)23
Skid steer¾ yd³ (0.57 m³)15
Backhoe front bucket1 yd³ (0.76 m³)12
Wheel loader2–3½ yd³ (1.5–2.7 m³)4–6

Bucket Fill Factor

The fill factor is how full a bucket gets per scoop, compared with its rated heaped capacity. Loose, moist material reaches 95–110%, gravel and sand 85–95%, and blasted rock 60–75%.

Frequently Asked Questions

How many yards is a skid steer bucket?

A skid steer bucket holds about ½–1 cubic yard (0.38–0.76 m³) heaped, depending on the machine size.

How many buckets fill a 10 yard dump truck?

A 10 yard dump truck takes about 12 scoops of a 1 yard bucket at 90% fill, or 4 scoops of a 3 yard wheel loader bucket.

What is a bucket cubic yard calculator used for?

A bucket cubic yard calculator plans how many scoops, passes and trucks a job needs, which sets the time and truck count for the job.

How many scoops of a skid steer fill a dump truck?

A ¾ yard skid steer bucket fills a 10 yard dump truck in about 15 scoops at 90% fill.

Is a heaped bucket the same as a struck bucket?

No, a heaped bucket holds material above the edge, and a struck bucket is filled level. Heaped capacity is larger.

How do I measure bucket capacity?

Check the bucket maker's plate or spec sheet, which lists the heaped capacity in cubic yards or cubic meters.