Bank, loose and compacted calculator
Enter bank cubic yards and the material to see the loose volume after digging and the compacted volume after placing. Loose yd³ = bank yd³ × (1 + swell %) and compacted yd³ = bank yd³ × (1 − shrinkage %).
How bank, loose and compacted calculator works?
The bank, loose and compacted calculator works in 2 steps: loose cubic yards = bank × (1 + swell), and compacted cubic yards = bank × (1 − shrinkage). Material presets fill typical swell and shrinkage values.
- Enter the bank (in-place) cubic yards.
- Pick the material, or custom.
- Adjust swell and shrinkage from a soil report.
- Read the loose and compacted volumes.
Bank, loose and compacted formula
The bank to loose formula is loose cubic yards (LCY) = bank cubic yards (BCY) × (1 + swell %).
LooseLCY = BCY × (1 + swell)CompactedCCY = BCY × (1 − shrinkage)Load factorLF = 1 ÷ (1 + swell)- BCY = bank cubic yards, in the ground
- LCY = loose cubic yards, in the truck
- CCY = compacted cubic yards, after placing
Bank, loose and compacted conversion chart
The bank, loose and compacted conversion chart lists the volumes for 10 bank cubic yards of each material.
| Material | Bank | Loose | Compacted | Load factor |
|---|---|---|---|---|
| Common earth | 10 | 12.5 | 9.0 | 0.80 |
| Clay | 10 | 13.5 | 8.5 | 0.74 |
| Sand and gravel | 10 | 11.2 | 9.4 | 0.89 |
| Topsoil | 10 | 13.0 | 8.5 | 0.77 |
Bank, Loose and Compacted Cubic Yards
There are 3 states of soil volume: bank (in place before digging), loose (after digging, in a truck or pile) and compacted (after placing and compacting). 10 bank cubic yards of common earth become 12.5 loose cubic yards at 25% swell and 9 compacted cubic yards at 10% shrinkage.
| Material | Typical swell | Typical shrinkage | Load factor |
|---|---|---|---|
| Common earth | 25% | 10% | 0.80 |
| Clay | 35% | 15% | 0.74 |
| Sand and gravel | 12% | 6% | 0.89 |
| Topsoil | 30% | 15% | 0.77 |
These are starting values. Moisture and soil type change swell and shrinkage, so use a soil report or test values for large jobs.
How to Use Bank and Loose Volumes
- Measure the hole or cut in bank cubic yards.
- Multiply by 1 + swell to size trucks and haul trips.
- Multiply by 1 − shrinkage to find the compacted fill it makes.
Frequently Asked Questions
What is a bank cubic yard?
A bank cubic yard is a cubic yard of soil measured in place in the ground, before digging.
How much does soil swell when dug?
Soil swells by about 10–40% when dug: about 12% for sand and gravel, 25% for common earth and 35% or more for clay.
What is a bulk cubic yard calculator?
A bulk cubic yard calculator converts in-place volume to the loose, bulked volume you haul, using the swell factor.
How many truckloads for 100 bank yards?
100 bank cubic yards of common earth swell to 125 loose yards, or 13 loads in 10 yard trucks.
Why is compacted volume less than bank volume?
Compacting packs soil tighter than its natural state, so compacted yards are 5–15% fewer than bank yards for most soils.
What is a load factor?
A load factor converts loose yards back to bank yards: bank = loose × load factor.