Enter your slab size and the price per cubic yard from your supplier to estimate the total cost of ready-mix concrete. Concrete cost = cubic yards ordered × price per cubic yard + delivery and short-load fees.
How concrete cost calculator works?
The concrete cost calculator works in 4 steps: it finds the cubic yards in the slab, rounds the order up to the nearest ¼ yd³ with 5% extra, prices the concrete, then adds the short-load fee, delivery and labor.
- Enter the slab length, width and thickness.
- Type the price per cubic yard from your ready-mix supplier.
- Add the delivery fee, the short-load fee and the order size where it applies.
- Add labor per square foot for a contractor quote, or leave it at $0 for DIY.
Concrete cost formula
The concrete cost formula is total cost = cubic yards ordered × price per cubic yard + fees + labor.
Total costcost = yd³ ordered × price + short-load fee + delivery + laborOrdered yardsyd³ ordered = ⌈L × W × T ÷ 27 × 1.05 × 4⌉ ÷ 4Cost per sq ft$/sq ft = total ÷ (L × W)- price = price per cubic yard (yd³) quoted by the plant
- short-load fee = flat charge on orders under the minimum load
- ⌈ ⌉ = round up to the next whole number
Concrete cost conversion chart
The concrete cost conversion chart shows how the short-load fee raises the cost per cubic yard on small orders, using $150 per yd³ and a $50 fee under 8 yd³ as example prices.
| Order | Concrete | Short-load fee | Total | Cost per yd³ |
|---|---|---|---|---|
| 1 yd³ (0.76 m³) | $150 | $50 | $200 | $200.00 |
| 2 yd³ (1.53 m³) | $300 | $50 | $350 | $175.00 |
| 3 yd³ (2.29 m³) | $450 | $50 | $500 | $166.67 |
| 5 yd³ (3.82 m³) | $750 | $50 | $800 | $160.00 |
| 8 yd³ (6.12 m³) | $1,200 | $0 | $1,200 | $150.00 |
| 10 yd³ (7.65 m³) | $1,500 | $0 | $1,500 | $150.00 |
Example prices only. Enter your local quote in the calculator.
How to Calculate Concrete Cost per Cubic Yard
To calculate the concrete cost per cubic yard, divide the total bill by the cubic yards delivered. There are 4 parts of a ready-mix concrete bill:
- Concrete: cubic yards ordered × price per cubic yard.
- Short-load fee: a flat charge on orders under the plant's minimum, often 8–10 yd³ (6–7.6 m³).
- Delivery: a fuel or distance charge from some suppliers.
- Labor: forming, pouring and finishing, priced per square foot by contractors.
The calculator rounds the order up to the nearest ¼ cubic yard and adds 5%, the way most suppliers take orders.
Concrete Cubic Yard Cost Example
A 20 × 12 ft slab 4 inches thick needs 2.96 yd³ (2.27 m³), and 3.25 yd³ ordered at $150 per yard costs $487.50 before fees. A $50 short-load fee brings the total to $537.50, or $2.24 per square foot. Prices in the example are placeholders: enter the quote from your local ready-mix plant.
Frequently Asked Questions
What is a short-load fee for concrete?
A short-load fee is a flat charge for concrete orders smaller than the plant's minimum load. The minimum is often 8–10 cubic yards (6–7.6 m³). Ask your supplier for the exact threshold and fee.
Is it cheaper to buy bags or ready-mix concrete?
Bags are usually cheaper for pours under about 1 cubic yard (0.76 m³), and ready-mix is usually cheaper above that. One cubic yard takes 45 bags of 80 lb mix, plus the time to mix them.
How do I find the concrete cost per square foot?
Divide the total concrete cost by the slab area in square feet. The calculator shows the cost per square foot under the results.
Why is a small concrete order more expensive per yard?
A small concrete order costs more per yard because of the short-load fee, a flat charge spread over fewer yards. 1 yd³ at $150 plus a $50 fee costs $200 per yard.
How much concrete is in a 10x10 slab and what does it cost?
A 10 × 10 ft slab 4 inches thick needs 1.23 cubic yards, ordered as 1.5 yd³, which costs $275 at $150 per yard plus a $50 short-load fee.
Does the concrete cost calculator include rebar or forms?
No, rebar, wire mesh, forms and gravel base are not included. Add them to the labor per square foot or price them separately.